Alaska Stat. § 09.10.054
This is the official text of Alaska Stat. § 09.10.054, part of Alaska’s Stat — part of the compiled statutory law of Alaska, published by the state as "Stat." Browse the sections below, each linked to its official government source.
Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.
Limits on when certain design, construction, and remodeling actions may be brought.
Official statutory text
(a) For actions covered under AS 09.45.881 09.45.899, a claimant may not begin an action against a construction professional unless the notice of claim under AS 09.45.881 is given within one year after the claimant discovers the defect that is the subject of the action, except that the action may not be begun more than 10 years after substantial completion of the dwelling construction or remodeling that contains or implements the alleged defect.
(b) A limitation imposed under this chapter for an action under AS 09.45.881 09.45.899 is tolled between the time the claimant serves notice under AS 09.45.881 and the time the claimant should reasonably understand that settlement under the procedures in AS 09.45.881 09.45.899 will not succeed.
(c) In this section, (1) action, claim, construction professional, and dwelling have the meanings given in AS 09.45.899 ;
(2) substantial completion means the date when the construction or remodeling is sufficiently completed to allow the owner of the dwelling or a person authorized by the owner to use or occupy the dwelling or the improvement to the dwelling in the manner for which the dwelling or improvement was intended.
(b) A limitation imposed under this chapter for an action under AS 09.45.881 09.45.899 is tolled between the time the claimant serves notice under AS 09.45.881 and the time the claimant should reasonably understand that settlement under the procedures in AS 09.45.881 09.45.899 will not succeed.
(c) In this section, (1) action, claim, construction professional, and dwelling have the meanings given in AS 09.45.899 ;
(2) substantial completion means the date when the construction or remodeling is sufficiently completed to allow the owner of the dwelling or a person authorized by the owner to use or occupy the dwelling or the improvement to the dwelling in the manner for which the dwelling or improvement was intended.
Status: in_force · Read it on the official government site
Need a lawyer in Alaska?
Find a Alaska lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.