Cal. PUC § 2811

This is the official text of Cal. PUC § 2811, part of California’s Public Utilities Code — regulates utilities such as electricity, gas, water, and transportation carriers.

Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.

Official statutory text

In order to promote the more efficient use and distribution of natural gas or electric energy and eliminate the necessity for construction of transmission facilities for gas or electricity produced by a private energy producer separate from those which may already exist to serve the same area and are owned and operated by a public utility subject to the jurisdiction and control of the Public Utilities Commission, the commission shall authorize the construction of an interconnection by a private energy producer upon application of such producer if the commission makes the findings required by Sections 2812 and 2812.5. The commission shall render its decision on any application filed pursuant to this chapter within 180 days of receipt of the application or at such later time as may be mutually agreed upon by the commission, the applicant, and the interconnecting public utility.

Status: in_force · Read it on the official government site

Need a lawyer in California?

Find a California lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.