Cal. PUC § 9513

This is the official text of Cal. PUC § 9513, part of California’s Public Utilities Code — regulates utilities such as electricity, gas, water, and transportation carriers.

Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.

Official statutory text

(a) A local publicly owned electric utility may require an additional one-time charge equal to three years of the annual fee described in Section 9512, for attachments reasonably shown to have been made without authorization that are discovered on or after January 1, 2012.

(b) A local publicly owned electric utility may remove an attachment made without authorization, if all of the following conditions are met:

(1) The owner of the attachment fails to pay the charge described in subdivision (a), if that charge is applicable.

(2) The owner of the attachment does not seek approval to attach pursuant to this part within a reasonable period of time.

(3) The owner of the attachment does not contest that the attachment was made without authorization.

(c) An attachment of a service drop wire is not made without authorization for the purposes of this section, if the owner of the attachment seeks approval to attach pursuant to this part within 45 days of the attachment.

Status: in_force · Read it on the official government site

Need a lawyer in California?

Find a California lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.