(a) The Director of Transportation shall prepare an annual report describing the status of the department’s progress in locating, assessing, and remediating barriers to fish passage. This report shall be given to the Legislature by October 31 of each year through the year 2025.
(b) Each report issued after October 31, 2016, shall include a status report on the remediation of barriers to fish passage on projects that have been identified pursuant to Section 156.5. The status report shall include, but is not limited to, all of the following information regarding a project identified pursuant to Section 156.5:
(1) Any updated information received by the department from the Department of Fish and Wildlife regarding the barriers to fish passage on the project.
(2) Whether funding has been committed to the project.
(3) The source of any funding for the project.
(4) The budget summary of the project.
(5) The status of inspections of culverts to ensure they are functioning properly and any other actions by the department to assess or remediate barriers to fish passage on the project.
(6) The applicable program initiation document work plan review.
(7) The estimated completion date for the project.
(b) Each report issued after October 31, 2016, shall include a status report on the remediation of barriers to fish passage on projects that have been identified pursuant to Section 156.5. The status report shall include, but is not limited to, all of the following information regarding a project identified pursuant to Section 156.5:
(1) Any updated information received by the department from the Department of Fish and Wildlife regarding the barriers to fish passage on the project.
(2) Whether funding has been committed to the project.
(3) The source of any funding for the project.
(4) The budget summary of the project.
(5) The status of inspections of culverts to ensure they are functioning properly and any other actions by the department to assess or remediate barriers to fish passage on the project.
(6) The applicable program initiation document work plan review.
(7) The estimated completion date for the project.
Status: in_force · Read it on the official government site
Need a lawyer in California?
Find a California lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.