§ 27A-102. Prompt payments to contractors.
Official statutory text
(a) If a construction contract between an owner and contractor does not provide for specific dates and times of payment, the owner shall pay to the contractor undisputed amounts owed under the terms of the written contract within the earlier of:
(1) 15 days after the day on which the occupancy permit is granted;
(2) 15 days after the day on which the owner or the owner's agent takes possession; or
(3) 15 days after an owner receives a contractor's payment request.
(b) If a food service contract between an owner and contractor does not provide for specific dates and times of payment, the owner shall pay to the contractor undisputed amounts owed under the terms of the written contract within the earlier of:
(1) 15 days after the day on which the owner or the owner's agent takes possession; or
(2) 15 days after an owner receives a contractor's payment request.
(c) If a contract provides for specific dates or times of payment, the owner shall pay to the contractor undisputed amounts owed within 7 days after the date or time specified in the contract.
(1) 15 days after the day on which the occupancy permit is granted;
(2) 15 days after the day on which the owner or the owner's agent takes possession; or
(3) 15 days after an owner receives a contractor's payment request.
(b) If a food service contract between an owner and contractor does not provide for specific dates and times of payment, the owner shall pay to the contractor undisputed amounts owed under the terms of the written contract within the earlier of:
(1) 15 days after the day on which the owner or the owner's agent takes possession; or
(2) 15 days after an owner receives a contractor's payment request.
(c) If a contract provides for specific dates or times of payment, the owner shall pay to the contractor undisputed amounts owed within 7 days after the date or time specified in the contract.
Status: in_force · Read it on the official government site
Need a lawyer in District of Columbia?
Find a District of Columbia lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.