61-536 LIABILITY OF SUPPLIERS.

Official statutory text

61-536. Liability of suppliers. No supplier of electric power or gas shall be liable for (a) actions taken pursuant to an order of the commission, or by reason of curtailment of such electric or gas service pursuant to such order or its curtailment plan on file with and approved by the commission; or (b) inability of a supplier to furnish adequate or sufficient supplies of electric power or gas or refusal to supply electric power or gas when such inability or refusal is due to inadequate or insufficient supplies on the supplier's system occurring as a result of the supplier's being unable to obtain from the commission an order which allows adequate time to construct necessary generating and transmission facilities.

History:

[61-536, added 1975, ch. 238, sec. 7, p. 646; am. 1976, ch. 219, sec. 1, p. 792.]

Status: in_force · Read it on the official government site

Need a lawyer in Idaho?

Find a Idaho lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.