§7–804.
Official statutory text
(a) On or before December 31, 2025, the Commission shall adopt regulations or issue orders to:
(1) implement specific policies for electric system planning;
(2) require consideration of investment in, or procurement of, cost–effective demand–side methods and technology to improve reliability and efficiency, including virtual power plants; and
(3) implement specific policies for improvements in order to promote the State’s policy goals under § 7–802 of this subtitle.
(b) The regulations adopted and orders issued under subsection (a) of this section shall:
(1) be developed with consideration given to the inherent differences, individual circumstances, and available resources among investor–owned electric companies, electric cooperatives, and municipal electric utilities; and
(2) if determined necessary by the Commission, establish separate requirements for investor–owned electric companies, electric cooperatives, and municipal electric utilities.
(1) implement specific policies for electric system planning;
(2) require consideration of investment in, or procurement of, cost–effective demand–side methods and technology to improve reliability and efficiency, including virtual power plants; and
(3) implement specific policies for improvements in order to promote the State’s policy goals under § 7–802 of this subtitle.
(b) The regulations adopted and orders issued under subsection (a) of this section shall:
(1) be developed with consideration given to the inherent differences, individual circumstances, and available resources among investor–owned electric companies, electric cooperatives, and municipal electric utilities; and
(2) if determined necessary by the Commission, establish separate requirements for investor–owned electric companies, electric cooperatives, and municipal electric utilities.
Status: in_force · Read it on the official government site
Need a lawyer in Maryland?
Find a Maryland lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.