Spoil material - Placement
Official statutory text
The operator shall place all excess spoil material resulting
from coal surface mining and reclamation activities in such a manner
that:
1. Spoil is transported and placed in a controlled manner in
position for concurrent compaction and in such a way to assure mass
stability and to prevent mass movement;
2. The areas of disposal are within the bonded permit areas and
all organic matter shall be removed immediately prior to spoil
placement;
3. Appropriate surface and internal drainage systems and
diversion ditches are used so as to prevent spoil erosion and
movement;
4. The disposal area does not contain springs, natural water
courses or wet weather seeps unless lateral drains are constructed
from the wet areas to the main underdrains in such a manner that
filtration of the water into the spoil pile will be prevented;
5. If placed on a slope, the spoil is placed upon the most
moderate slope among those upon which, in the judgment of the
Department, the spoil could be placed in compliance with all the
requirements of this act, and shall be placed, where possible, upon,
or above, a natural terrace, bench, or berm, if such placement
provides additional stability and prevents mass movement;
6. Where the toe of the spoil rests on a downslope, a rock toe
buttress, of sufficient size to prevent mass movement, is
constructed;
7. The final configuration is compatible with the natural
drainage pattern and surroundings and suitable for intended uses;
8. Design of the spoil disposal area is certified by a
qualified registered professional engineer in conformance with
professional standards; and
9. All other provisions of this act are met.
from coal surface mining and reclamation activities in such a manner
that:
1. Spoil is transported and placed in a controlled manner in
position for concurrent compaction and in such a way to assure mass
stability and to prevent mass movement;
2. The areas of disposal are within the bonded permit areas and
all organic matter shall be removed immediately prior to spoil
placement;
3. Appropriate surface and internal drainage systems and
diversion ditches are used so as to prevent spoil erosion and
movement;
4. The disposal area does not contain springs, natural water
courses or wet weather seeps unless lateral drains are constructed
from the wet areas to the main underdrains in such a manner that
filtration of the water into the spoil pile will be prevented;
5. If placed on a slope, the spoil is placed upon the most
moderate slope among those upon which, in the judgment of the
Department, the spoil could be placed in compliance with all the
requirements of this act, and shall be placed, where possible, upon,
or above, a natural terrace, bench, or berm, if such placement
provides additional stability and prevents mass movement;
6. Where the toe of the spoil rests on a downslope, a rock toe
buttress, of sufficient size to prevent mass movement, is
constructed;
7. The final configuration is compatible with the natural
drainage pattern and surroundings and suitable for intended uses;
8. Design of the spoil disposal area is certified by a
qualified registered professional engineer in conformance with
professional standards; and
9. All other provisions of this act are met.
Status: in_force · Read it on the official government site
Need a lawyer in Oklahoma?
Find a Oklahoma lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.