Temporary clearance of lines - Costs
Official statutory text
When any person, firm or corporation desires to temporarily
carry on any function, activity, work or operation in closer
proximity to any high-voltage line or conductor than permitted by
Oklahoma Statutes - Title 63. Public Health and Safety Page 1304
this act, the person or persons responsible for the work to be done
shall promptly notify the operator of the high-voltage conductors of
the work to be performed and make appropriate arrangements with the
operator of the high-voltage conductors for temporary mechanical
barriers, temporary deenergization and grounding of the conductors,
or temporarily raising of the conductors before proceeding with any
work which would impair the clearances required by this act.
The actual costs incurred by any operator of high-voltage
conductors in providing clearances as above set out shall be paid by
the persons, firms or corporations requesting the operator of the
high-voltage conductors to provide said temporary clearances. Unless
and until arrangements satisfactory to the operator of the high-
voltage conductors for such payment have been made, such operator
shall be under no duty to provide clearances as set out herein.
carry on any function, activity, work or operation in closer
proximity to any high-voltage line or conductor than permitted by
Oklahoma Statutes - Title 63. Public Health and Safety Page 1304
this act, the person or persons responsible for the work to be done
shall promptly notify the operator of the high-voltage conductors of
the work to be performed and make appropriate arrangements with the
operator of the high-voltage conductors for temporary mechanical
barriers, temporary deenergization and grounding of the conductors,
or temporarily raising of the conductors before proceeding with any
work which would impair the clearances required by this act.
The actual costs incurred by any operator of high-voltage
conductors in providing clearances as above set out shall be paid by
the persons, firms or corporations requesting the operator of the
high-voltage conductors to provide said temporary clearances. Unless
and until arrangements satisfactory to the operator of the high-
voltage conductors for such payment have been made, such operator
shall be under no duty to provide clearances as set out herein.
Status: in_force · Read it on the official government site
Need a lawyer in Oklahoma?
Find a Oklahoma lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.