§ 16.071. NOTICE REQUIREMENTS.
Official statutory text
(a) A contract stipulation that requires a claimant to give notice of a claim for damages as a condition precedent to the right to sue on the contract is not valid unless the stipulation is reasonable. A stipulation that requires notification within less than 90 days is void.
(b) If notice is required, the claimant may notify any convenient agent of the company that requires the notice.
(c) A contract stipulation between the operator of a railroad, street railway, or interurban railroad and an employee or servant of the operator is void if it requires as a condition precedent to liability:
(1) the employee or servant to notify the system of a claim for damages for personal injury caused by negligence; or
(2) the spouse, parent, or child of a deceased employee or servant to notify the system of a claim of death caused by negligence.
(d) This section applies to a contract between a federal prime contractor and a subcontractor, except that the notice period stipulated in the subcontract may be for a period not less than the period stipulated in the prime contract, minus seven days.
(e) In a suit covered by this section or Section 16.070, it is presumed that any required notice has been given unless lack of notice is specifically pleaded under oath.
(f) This section does not apply to a contract relating to the sale or purchase of a business entity if a party to the contract pays or receives or is obligated to pay or receive consideration under the contract having an aggregate value of not less than $500,000.
(b) If notice is required, the claimant may notify any convenient agent of the company that requires the notice.
(c) A contract stipulation between the operator of a railroad, street railway, or interurban railroad and an employee or servant of the operator is void if it requires as a condition precedent to liability:
(1) the employee or servant to notify the system of a claim for damages for personal injury caused by negligence; or
(2) the spouse, parent, or child of a deceased employee or servant to notify the system of a claim of death caused by negligence.
(d) This section applies to a contract between a federal prime contractor and a subcontractor, except that the notice period stipulated in the subcontract may be for a period not less than the period stipulated in the prime contract, minus seven days.
(e) In a suit covered by this section or Section 16.070, it is presumed that any required notice has been given unless lack of notice is specifically pleaded under oath.
(f) This section does not apply to a contract relating to the sale or purchase of a business entity if a party to the contract pays or receives or is obligated to pay or receive consideration under the contract having an aggregate value of not less than $500,000.
Status: in_force · Read it on the official government site
Need a lawyer in Texas?
Find a Texas lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.