Tex. Local Government Code § 214.904
This is the official text of Tex. Local Government Code § 214.904, part of Texas’s Local Government Code — governs the powers and operations of Texas cities and counties.
Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.
§ 214.904. TIME FOR ISSUANCE OF MUNICIPAL BUILDING PERMIT.
Official statutory text
(a) This section applies only to a permit required by a municipality to erect or improve a building or other structure in the municipality or its extraterritorial jurisdiction.
(b) Not later than the 45th day after the date an application for a permit is submitted, the municipality must:
(1) grant or deny the permit;
(2) provide written notice to the applicant stating the reasons why the municipality has been unable to grant or deny the permit application; or
(3) reach a written agreement with the applicant providing for a deadline for granting or denying the permit.
(c) For a permit application for which notice is provided under Subsection (b)(2), the municipality must grant or deny the permit not later than the 30th day after the date the notice is received.
(d) If a municipality fails to grant or deny a permit application in the time required by Subsection (c) or by an agreement under Subsection (b)(3), the municipality:
(1) may not collect any permit fees associated with the application; and
(2) shall refund to the applicant any permit fees associated with the application that have been collected.
(b) Not later than the 45th day after the date an application for a permit is submitted, the municipality must:
(1) grant or deny the permit;
(2) provide written notice to the applicant stating the reasons why the municipality has been unable to grant or deny the permit application; or
(3) reach a written agreement with the applicant providing for a deadline for granting or denying the permit.
(c) For a permit application for which notice is provided under Subsection (b)(2), the municipality must grant or deny the permit not later than the 30th day after the date the notice is received.
(d) If a municipality fails to grant or deny a permit application in the time required by Subsection (c) or by an agreement under Subsection (b)(3), the municipality:
(1) may not collect any permit fees associated with the application; and
(2) shall refund to the applicant any permit fees associated with the application that have been collected.
Status: in_force · Read it on the official government site
Need a lawyer in Texas?
Find a Texas lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.