§ 284.154. MUNICIPAL REVIEW PROCESS.
Official statutory text
(a) A municipality shall process each permit application on a nondiscriminatory basis.
(b) Not later than the 30th day after the date the municipality receives an application for a permit for a network node or node support pole, or the 10th day after the date the municipality receives an application for a permit for a transport facility, the municipality shall determine whether the application is complete and notify the applicant of that determination. If the municipality determines that the application is not complete, the municipality shall specifically identify the missing information.
(c) A municipality shall approve an application that does not require zoning or land use approval under this chapter unless the application or the corresponding work to be performed under the permit does not comply with the municipality's applicable codes or other municipal rules, regulations, or other law that is consistent with this chapter.
(d) A municipality must approve or deny an application for a node support pole not later than the 150th day after the date the municipality receives the complete application. A municipality must approve or deny an application for a network node not later than the 60th day after the date the municipality receives the complete application. A municipality must approve or deny an application for a transport facility not later than the 21st day after the date the municipality receives a complete application. An application for a permit for a node support pole, network node, or transport facility shall be deemed approved if the application is not approved or denied on or before the applicable date for approval or denial prescribed by this subsection.
(e) A municipality that denies a complete application must document the basis for the denial, including the specific applicable code provisions or other municipal rules, regulations, or other law on which the denial was based. The municipality shall send the documentation by electronic mail to the applicant on or before the date the municipality denies the application.
(f) Not later than the 30th day after the date the municipality denies the application, the applicant may cure the deficiencies identified in the denial documentation and resubmit the application without paying an additional application fee, other than a fee for actual costs incurred by the municipality. Notwithstanding Subsection (d), the municipality shall approve or deny the revised completed application after a denial not later than the 90th day after the date the municipality receives the completed revised application. The municipality's review of the revised application is limited to the deficiencies cited in the denial documentation.
(b) Not later than the 30th day after the date the municipality receives an application for a permit for a network node or node support pole, or the 10th day after the date the municipality receives an application for a permit for a transport facility, the municipality shall determine whether the application is complete and notify the applicant of that determination. If the municipality determines that the application is not complete, the municipality shall specifically identify the missing information.
(c) A municipality shall approve an application that does not require zoning or land use approval under this chapter unless the application or the corresponding work to be performed under the permit does not comply with the municipality's applicable codes or other municipal rules, regulations, or other law that is consistent with this chapter.
(d) A municipality must approve or deny an application for a node support pole not later than the 150th day after the date the municipality receives the complete application. A municipality must approve or deny an application for a network node not later than the 60th day after the date the municipality receives the complete application. A municipality must approve or deny an application for a transport facility not later than the 21st day after the date the municipality receives a complete application. An application for a permit for a node support pole, network node, or transport facility shall be deemed approved if the application is not approved or denied on or before the applicable date for approval or denial prescribed by this subsection.
(e) A municipality that denies a complete application must document the basis for the denial, including the specific applicable code provisions or other municipal rules, regulations, or other law on which the denial was based. The municipality shall send the documentation by electronic mail to the applicant on or before the date the municipality denies the application.
(f) Not later than the 30th day after the date the municipality denies the application, the applicant may cure the deficiencies identified in the denial documentation and resubmit the application without paying an additional application fee, other than a fee for actual costs incurred by the municipality. Notwithstanding Subsection (d), the municipality shall approve or deny the revised completed application after a denial not later than the 90th day after the date the municipality receives the completed revised application. The municipality's review of the revised application is limited to the deficiencies cited in the denial documentation.
Status: in_force · Read it on the official government site
Need a lawyer in Texas?
Find a Texas lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.