§ 302.006. METER GUARANTEES.

Official statutory text

(a) This section applies to any energy savings performance contract that:

(1) provides for any metering or related equipment, system, or process or procedure; and

(2) includes a meter guarantee by the provider, regardless of whether the meter guarantee is a part of a broader guarantee applicable to other energy or water conservation or usage measures or causally connected work.

(b) Not later than the fifth anniversary of the effective date of an energy savings performance contract, an engineer shall test a statistically relevant sample of the meters installed or implemented under the contract to determine or calculate the actual average accuracy and shall compare the actual average accuracy to the baseline average accuracy of those tested meters.

(c) A meter guarantee applies if the engineer reports to the local government and the provider that the average accuracy of the tested meters as of the testing date is less than the baseline average accuracy of the tested meters as of the testing date.

(d) The amount payable under the meter guarantee must be determined for each year subject to the engineer's report and is equal to the difference between:

(1) the agreed increase in billable revenues based on the estimated accuracy of all of the meters for each year, according to the energy savings performance contract; and

(2) the revenues for the same year that would result from applying the engineer's reported actual average accuracy of the tested meters to all of the meters subject to the energy savings performance contract, using the same contract components that were used to calculate the agreed increase in billable revenues for that year, assuming the annual decrease in actual average accuracy of all the meters was a pro rata percentage of the reported total decrease in actual average accuracy.

(e) Notwithstanding Subsection (d), if the meter guarantee in the contract is part of a broader guarantee applicable to other energy or water conservation or usage measures or causally connected work under the contract, the amount payable under the meter guarantee for any year during the measurement period is reduced or offset by the difference between:

(1) the sum of the energy savings and the increase in billable revenues resulting from the other energy or water conservation or usage measures or causally connected work for that year during the measurement period; and

(2) the guaranteed amount of the energy savings and the increase in billable revenues from the other energy or water conservation or usage measures or causally connected work for that year during the measurement period.

(f) A test conducted under this section must be performed in accordance with the procedures established by the International Performance Measurement and Verification Protocol or succeeding standards of the United States Department of Energy.

(g) An engineer conducting a test under this section shall:

(1) verify that the tested meters have been properly maintained and are operating properly; and

(2) comply with Section 302.005(c).

Status: in_force · Read it on the official government site

Need a lawyer in Texas?

Find a Texas lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.