§ 36.053. COMPONENTS OF INVESTED CAPITAL.
Official statutory text
(a) Electric utility rates shall be based on the original cost, less depreciation, of property used by and useful to the utility in providing service.
(b) The original cost of property shall be determined at the time the property is dedicated to public use, whether by the utility that is the present owner or by a predecessor.
(c) In this section, the term "original cost" means the actual money cost or the actual money value of consideration paid other than money.
(d) If the commission issues a certificate of convenience and necessity or if the commission, acting under the authority formerly provided by Section 39.203(e), ordered an electric utility or a transmission and distribution utility to construct or enlarge transmission or transmission-related facilities to facilitate meeting the goal for generating capacity from renewable energy technologies under former Section 39.904(a), the commission shall find that the facilities are used and useful to the utility in providing service for purposes of this section and are prudent and includable in the rate base, regardless of the extent of the utility's actual use of the facilities.
(b) The original cost of property shall be determined at the time the property is dedicated to public use, whether by the utility that is the present owner or by a predecessor.
(c) In this section, the term "original cost" means the actual money cost or the actual money value of consideration paid other than money.
(d) If the commission issues a certificate of convenience and necessity or if the commission, acting under the authority formerly provided by Section 39.203(e), ordered an electric utility or a transmission and distribution utility to construct or enlarge transmission or transmission-related facilities to facilitate meeting the goal for generating capacity from renewable energy technologies under former Section 39.904(a), the commission shall find that the facilities are used and useful to the utility in providing service for purposes of this section and are prudent and includable in the rate base, regardless of the extent of the utility's actual use of the facilities.
Status: in_force · Read it on the official government site
Need a lawyer in Texas?
Find a Texas lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.