Tex. Utilities Code § 36.205

This is the official text of Tex. Utilities Code § 36.205, part of Texas’s Utilities Code — regulates utility companies.

Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.

§ 36.205. PURCHASED POWER COST RECOVERY.

Official statutory text

(a) This section applies only to an increase or decrease in the cost of purchased electricity that has been:

(1) accepted by a federal regulatory authority; or

(2) approved after a hearing by the commission.

(b) The commission may use any appropriate method to provide for the adjustment of the cost of purchased electricity on terms determined by the commission.

(c) Purchased electricity costs may be recovered:

(1) concurrently with the effective date of the changed costs to the purchasing electric utility; or

(2) as soon after the effective date as reasonably practical.

(d) The commission may provide a mechanism to allow an electric utility that has a noncontiguous geographical service area and that purchases power for resale for that noncontiguous service area from electric utilities that are not members of the Electric Reliability Council of Texas to recover purchased power costs for the area in a manner that reflects the purchased power cost for that specific geographical noncontiguous area. The commission may not require an electric cooperative corporation to use the mechanism provided under this section unless the electric cooperative corporation requests its use.

(e) Notwithstanding Subsection (a), an electric utility may apply to the commission for review and approval of an agreement between the electric utility and another person for the purchase of power by the electric utility if approval by the commission is a pre-condition to the effectiveness of the electric utility's right or obligation to purchase power under the agreement. This subsection applies only to an agreement with a term of three years or more. The commission by rule shall implement this subsection consistent with the standards and procedures in the commission's rules governing contested cases on certificates of convenience and necessity for generating facilities adopted under Sections 37.056 and 37.058. This subsection expires September 1, 2033.

Status: in_force · Read it on the official government site

Need a lawyer in Texas?

Find a Texas lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.