Processing of payments

Official statutory text

(a) (1) When a contractor submits a properly prepared request for payment of work completed on state construction projects and the request for payment conforms with the provisions of the contract award and laws of the State of Arkansas, the following maximum time is allowed for the processing of the payment requests by the various parties involved, excluding time required for transmittal from one (1) party to another: (A) A design professional - five (5) working days; (B) A state agency or institution of higher education exempt from review and approval by the Building Authority Division - five (5) working days, including preparation of a voucher and submission for payment; and (C) The Department of Finance and Administration - five (5) working days. (2) Should payment be contested by any of the parties listed in this subsection, it shall be the responsibility of the parties contesting the payment, within the time specified for processing payment, to notify the contractor involved that payment has been contested and reasons therefor. (3) Should any of the parties listed in this subsection fail to properly process uncontested requests for payments within the time limits specified following date of receipt, a penalty of eight percent (8%) per annum of the amount of the request for payment shall be assessed against the parties responsible for the delay. (b) (1) The Chief Fiscal Officer of the State shall establish procedures for monitoring payments to contractors. When it has been determined that payment processing has exceeded the time limits established in this section, the Chief Fiscal Officer of the State shall cause an investigation to be made for the purpose of determining the responsible parties and the amount of penalty to be paid. (2) Penalties assessed for failure to comply with the provisions in this section shall be paid to the contractor by the parties responsible in accordance with procedures established by the Chief Fiscal Officer of the State. Amended by Act 2019, No. 910,§ 6084, eff. 7/1/2019. Acts 1973, No. 876, § 22; 1977, No. 813, § 3; 1979, No. 833, § 9; A.S.A. 1947, § 13-348; Acts 2001, No. 214, § 4; 2001, No. 961, § 6; 2003, No. 364, § 6.

(a) (1) When a contractor submits a properly prepared request for payment of work completed on state construction projects and the request for payment conforms with the provisions of the contract award and laws of the State of Arkansas, the following maximum time is allowed for the processing of the payment requests by the various parties involved, excluding time required for transmittal from one (1) party to another: (A) A design professional - five (5) working days; (B) A state agency or institution of higher education exempt from review and approval by the Building Authority Division - five (5) working days, including preparation of a voucher and submission for payment; and (C) The Department of Finance and Administration - five (5) working days. (2) Should payment be contested by any of the parties listed in this subsection, it shall be the responsibility of the parties contesting the payment, within the time specified for processing payment, to notify the contractor involved that payment has been contested and reasons therefor. (3) Should any of the parties listed in this subsection fail to properly process uncontested requests for payments within the time limits specified following date of receipt, a penalty of eight percent (8%) per annum of the amount of the request for payment shall be assessed against the parties responsible for the delay.
the contractor involved that payment has been contested and reasons therefor. (3) Should any of the parties listed in this subsection fail to properly process uncontested requests for payments within the time limits specified following date of receipt, a penalty of eight percent (8%) per annum of the amount of the request for payment shall be assessed against the parties responsible for the delay.

(1) When a contractor submits a properly prepared request for payment of work completed on state construction projects and the request for payment conforms with the provisions of the contract award and laws of the State of Arkansas, the following maximum time is allowed for the processing of the payment requests by the various parties involved, excluding time required for transmittal from one (1) party to another: (A) A design professional - five (5) working days; (B) A state agency or institution of higher education exempt from review and approval by the Building Authority Division - five (5) working days, including preparation of a voucher and submission for payment; and (C) The Department of Finance and Administration - five (5) working days.

(A) A design professional - five (5) working days;

(B) A state agency or institution of higher education exempt from review and approval by the Building Authority Division - five (5) working days, including preparation of a voucher and submission for payment; and

(C) The Department of Finance and Administration - five (5) working days.

(2) Should payment be contested by any of the parties listed in this subsection, it shall be the responsibility of the parties contesting the payment, within the time specified for processing payment, to notify the contractor involved that payment has been contested and reasons therefor.

(3) Should any of the parties listed in this subsection fail to properly process uncontested requests for payments within the time limits specified following date of receipt, a penalty of eight percent (8%) per annum of the amount of the request for payment shall be assessed against the parties responsible for the delay.

(b) (1) The Chief Fiscal Officer of the State shall establish procedures for monitoring payments to contractors. When it has been determined that payment processing has exceeded the time limits established in this section, the Chief Fiscal Officer of the State shall cause an investigation to be made for the purpose of determining the responsible parties and the amount of penalty to be paid. (2) Penalties assessed for failure to comply with the provisions in this section shall be paid to the contractor by the parties responsible in accordance with procedures established by the Chief Fiscal Officer of the State.

(1) The Chief Fiscal Officer of the State shall establish procedures for monitoring payments to contractors. When it has been determined that payment processing has exceeded the time limits established in this section, the Chief Fiscal Officer of the State shall cause an investigation to be made for the purpose of determining the responsible parties and the amount of penalty to be paid.

(2) Penalties assessed for failure to comply with the provisions in this section shall be paid to the contractor by the parties responsible in accordance with procedures established by the Chief Fiscal Officer of the State.

Amended by Act 2019, No. 910,§ 6084, eff. 7/1/2019.

Acts 1973, No. 876, § 22; 1977, No. 813, § 3; 1979, No. 833, § 9; A.S.A. 1947, § 13-348; Acts 2001, No. 214, § 4; 2001, No. 961, § 6; 2003, No. 364, § 6.

Status: in_force

Need a lawyer in Arkansas?

Find a Arkansas lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.