(a) If a contract for CMGC services is entered into pursuant to this chapter and includes preconstruction services by the construction manager, the San Diego Association of Governments shall enter into a written contract with the construction manager for preconstruction services, under which the San Diego Association of Governments shall pay the construction manager a fee for preconstruction services in an amount agreed upon by the San Diego Association of Governments and the construction manager. The preconstruction services contract may include fees for services to be performed during the contract period; provided, however, the San Diego Association of Governments shall not request or obtain a fixed price or a guaranteed maximum price for the construction contract from the construction manager or enter into a construction contract with the construction manager until after the San Diego Association of Governments has entered into a services contract. A preconstruction services contract shall provide for the subsequent negotiation for construction of all or any discrete phase or phases of the project and shall provide for the San Diego Association of Governments to own the design plans and other preconstruction services work product.

(b) A contract for construction services will be awarded after the plans have been sufficiently developed and either a fixed price or a guaranteed maximum price has been successfully negotiated. In the event that a fixed price or a guaranteed maximum price is not negotiated, the San Diego Association of Governments may award the contract for construction services utilizing any other procurement method authorized by law.

(c) The construction manager shall perform not less than 30 percent of the work covered by the fixed price or guaranteed maximum price agreement reached. Work that is not performed directly by the construction manager shall be bid to subcontractors pursuant to Section 6955.

Status: in_force · Read it on the official government site

Need a lawyer in California?

Find a California lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.