Cal. PUC § 1002.4

This is the official text of Cal. PUC § 1002.4, part of California’s Public Utilities Code — regulates utilities such as electricity, gas, water, and transportation carriers.

Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.

Official statutory text

(a) The commission may, by resolution, adopt successor guidelines to the commission’s Guidelines for Energy Project Applications Requiring CEQA Compliance: Pre-filing and Proponent’s Environmental Assessments (November 2019) at a publicly noticed meeting to address its receipt and review of and actions on applications for the construction of electrical transmission facilities subject to its regulatory jurisdiction. These guidelines shall be designed to mitigate ratepayer costs, lessen the uncertainty of the submittal process, and improve the commission’s review process by increasing applicant understanding of applicable requirements with the intent of advancing the timely resolution of the construction of the facilities and efficient disposition of the applications.

(b) To the extent there is a conflict or inconsistency between the content in the guidelines adopted or revised pursuant to this section and a commission rule of practice or procedure addressing the completeness of applications for electrical transmission facilities, the guidelines shall prevail.

(c) The guidelines adopted pursuant to this section shall supersede the commission’s Guidelines for Energy Project Applications Requiring CEQA Compliance: Pre-filing and Proponent’s Environmental Assessments (November 2019), unless the guidelines adopted pursuant to this section specify otherwise.

(d) Notwithstanding any other law, guidelines adopted pursuant to this section are exempt from the requirements of Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code.

(e) For purposes of this section, “electrical transmission facilities” means electrical generation facilities, transmission, power, and distribution line facilities, and substations, as described in commission General Order No. 131-D, as it may be amended from time to time.

Status: in_force · Read it on the official government site

Need a lawyer in California?

Find a California lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.