§ 27A-104. Prompt payments to subcontractors.
Official statutory text
(a) If a contract is between a contractor and subcontractor, or between subcontractors, the contractor or subcontractor shall pay undisputed amounts owed to its subcontractor within 7 days after receipt by the contractor or subcontractor of each payment received for its subcontractors' work or materials.
(b) Notwithstanding subsection (a) of this section, conditions of payment to the subcontractor on receipt by the contractor of payment from the owner may not abrogate or waive the right of the subcontractor to:
(1) Claim a mechanics' lien; or
(2) Sue on a contractor's bond.
(c) Any provision of a contract made in violation of subsection (b) of this section is void as against the public policy of the District.
(d) (1) A contractor or subcontractor shall not deduct or withhold a subcontractor's or lower-tiered subcontractor's payment for the purpose of offsetting any other contractual obligation or work to be completed.
(2) Any contract or subcontract provision in a contract executed after March 31, 2023, that allows a contracting party to withhold funds due under one contract or subcontract for alleged claims or damages due on another contract or subcontract is void as against public policy.
(b) Notwithstanding subsection (a) of this section, conditions of payment to the subcontractor on receipt by the contractor of payment from the owner may not abrogate or waive the right of the subcontractor to:
(1) Claim a mechanics' lien; or
(2) Sue on a contractor's bond.
(c) Any provision of a contract made in violation of subsection (b) of this section is void as against the public policy of the District.
(d) (1) A contractor or subcontractor shall not deduct or withhold a subcontractor's or lower-tiered subcontractor's payment for the purpose of offsetting any other contractual obligation or work to be completed.
(2) Any contract or subcontract provision in a contract executed after March 31, 2023, that allows a contracting party to withhold funds due under one contract or subcontract for alleged claims or damages due on another contract or subcontract is void as against public policy.
Status: in_force · Read it on the official government site
Need a lawyer in District of Columbia?
Find a District of Columbia lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.