Ind. Code § 8-1-27-12

This is the official text of Ind. Code § 8-1-27-12, part of Indiana’s Code — part of the compiled statutory law of Indiana, published by the state as "Code." Browse the sections below, each linked to its official government source.

Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.

Recovery of costs by public utility for capital projects or implemented plan

Official statutory text

Sec. 12. (a) If the commission issues an order approving an environmental compliance plan submitted by a public utility under this chapter, the commission shall, absent fraud, concealment, gross mismanagement, or inadequate quality control, allow the public utility to do the following:

(1) If a public utility is allowed by law to earn a return on the public utility's investment, the public utility may add to the fair value of the public utility's property the fair value of a completed capital project, or part of a capital project, that:

(A) is constructed and consists of:

(i) new systems, equipment, or facilities; or

(ii) modifications to existing systems, equipment, or facilities; and

(B) is part of the environmental compliance plan approved by the commission;

up to the amount approved under section 8(2) or 13 of this chapter, whichever is applicable.

(2) The public utility may recover the costs incurred by the public utility in the development and implementation of the approved environmental compliance plan up to the amount approved under section 8(2) or 13 of this chapter, whichever is applicable.

(b) The public utility may not recover costs in excess of the cost estimate approved by the commission under section 8(2) or 13 of this chapter, whichever is applicable, unless the commission finds that the additional costs were necessary and prudent.

(c) Except as provided in subsection (d), costs otherwise recoverable by a public utility under subsections (a) and (b) shall be recovered only through a general rate proceeding for the public utility and, to the extent such costs provide the public utility with a return of, or return on, the public utility's investment in a completed capital project, or a part of a capital project, such costs shall be so recovered only if the capital project, or part of the capital project, is found by the commission to be used and useful.

(d) Costs otherwise recoverable by a public utility under subsections (a) and (b) that also qualify for recovery under IC 8-1-2-6.6 shall be recovered by the public utility when and as provided under IC 8-1-2-6.6.

(e) This section does not apply if the public utility elects the review described in section 19 of this chapter.

As added by P.L.76-1991, SEC.1.

Status: in_force · Read it on the official government site

Need a lawyer in Indiana?

Find a Indiana lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.