Ind. Code § 8-1-39-11

This is the official text of Ind. Code § 8-1-39-11, part of Indiana’s Code — part of the compiled statutory law of Indiana, published by the state as "Code." Browse the sections below, each linked to its official government source.

Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.

Extension of gas or electric service to targeted economic development project; approval by Indiana economic development corporation of costs as TDSIC costs; rural gas service

Official statutory text

Sec. 11. (a) The extension, construction, addition, or improvement of the plant and equipment of a public utility that is installed to provide gas or electric service to a targeted economic development project is used and useful in the public service.

(b) A public utility shall apply to the Indiana economic development corporation for approval to treat costs associated with a targeted economic development project as TDSIC costs. Costs approved by the Indiana economic development corporation shall be treated as TDSIC costs and may be recovered through a TDSIC under section 12 of this chapter. The TDSIC revenues associated with a targeted economic development project shall not be included in a public utility's total retail revenues for purposes of determining an aggregate increase under section 14 of this chapter.

(c) Notwithstanding any law or rule governing extension of service, a public utility that provides gas service may, on a nondiscriminatory basis, extend service in rural areas without a deposit or other adequate assurance of performance from the customer, to the extent that the extension of service results in a positive contribution to the utility's overall cost of service over a twenty (20) year period. However, if the public utility determines that the extension of service to a targeted economic development project will not result in a positive contribution to the utility's overall cost of service over a twenty (20) year period, the public utility may require a deposit or other adequate assurance of performance from:

(1) the developer of the targeted economic development project; or

(2) a local, regional, or state economic development organization.

As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019, SEC.5.

Status: in_force · Read it on the official government site

Need a lawyer in Indiana?

Find a Indiana lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.