Ind. Code § 8-1-7.9-22

This is the official text of Ind. Code § 8-1-7.9-22, part of Indiana’s Code — part of the compiled statutory law of Indiana, published by the state as "Code." Browse the sections below, each linked to its official government source.

Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.

Petition for approval of project to serve large load customer; requirements for submission; financial assurances by large load customer; projects serving multiple locations or customers

Official statutory text

Sec. 22. (a) This section applies to an energy utility that petitions the commission for approval of a project to serve a large load customer.

(b) An energy utility may submit to the commission a petition for approval of a project to serve a large load customer only if the following are satisfied:

(1) The petition concerns serving the energy needs of a large load customer.

(2) The large load customer commits to significant and meaningful financial assurances that must:

(A) include reimbursement by the large load customer of at least eighty percent (80%) of the project costs reasonably allocable to the large load customer; and

(B) afford protections for the energy utility's existing and future customers from project costs reasonably allocable to the large load customer regardless of whether the large load customer ultimately takes service in the anticipated amount and within the anticipated time frame.

(3) At least thirty (30) days before the energy utility's submission of the petition to the commission, the energy utility held at least one (1) pre-filing meeting with:

(A) the corporation;

(B) the office;

(C) the office of utility consumer counselor;

(D) the appropriate regional transmission organization; and

(E) the large load customer;

to review the project.

(c) An energy utility may petition the commission for approval of a project to serve:

(1) one (1) or more large load customers at one (1) or more locations; or

(2) not more than four (4) customers whose aggregate demand satisfies the amount set forth in section 10(1) of this chapter.

In any case in which more than one (1) large load customer is to be served by a project, a reference in this chapter to one (1) large load customer is a reference to all large load customers to be served by the project, in accordance with IC 1-1-4-1(3).

(d) In submitting a petition to the commission under this section, an energy utility must demonstrate that the large load customer and the associated projects meet the requirements of this chapter.

As added by P.L.217-2025, SEC.2.

Status: in_force · Read it on the official government site

Need a lawyer in Indiana?

Find a Indiana lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.