Inclusion in integrated resource plan of information regarding advanced transmission technologies and utility's transmission and distribution systems
Official statutory text
Sec. 3.4. (a) As used in this section, "advanced transmission technologies" means software or hardware technologies that increase the capacity, efficiency, reliability, or safety of an existing or new electric transmission facility, including:
(1) grid enhancing technologies, such as dynamic line rating, advanced power flow controllers, and topology optimization;
(2) advanced conductors; and
(3) other technologies designed to:
(A) reduce transmission congestion; or
(B) increase the capacity, efficiency, reliability, or safety of an existing or new electric transmission facility.
(b) As used in this section, "electric utility" refers to an electric utility that:
(1) is listed in 170 IAC 4-7-2(a); and
(2) owns and operates a transmission or distribution system.
(c) In any integrated resource plan filed with the commission under 170 IAC 4-7 after December 31, 2025, an electric utility must include a description of the potential use of, or investment in, one (1) or more advanced transmission technologies to enable the electric utility to safely, reliably, efficiently, and cost effectively meet electric system demand, taking into consideration cost, risk, uncertainty, and the alternative investments needed to build new transmission infrastructure if advanced transmission technologies are not deployed.
(d) In any integrated resource plan filed with the commission under 170 IAC 4-7 after December 31, 2029, an electric utility must include a description of the electric utility's transmission and distribution systems, as applicable, as specified by the commission under 170 IAC 4-7.
As added by P.L.10-2025, SEC.1.
(1) grid enhancing technologies, such as dynamic line rating, advanced power flow controllers, and topology optimization;
(2) advanced conductors; and
(3) other technologies designed to:
(A) reduce transmission congestion; or
(B) increase the capacity, efficiency, reliability, or safety of an existing or new electric transmission facility.
(b) As used in this section, "electric utility" refers to an electric utility that:
(1) is listed in 170 IAC 4-7-2(a); and
(2) owns and operates a transmission or distribution system.
(c) In any integrated resource plan filed with the commission under 170 IAC 4-7 after December 31, 2025, an electric utility must include a description of the potential use of, or investment in, one (1) or more advanced transmission technologies to enable the electric utility to safely, reliably, efficiently, and cost effectively meet electric system demand, taking into consideration cost, risk, uncertainty, and the alternative investments needed to build new transmission infrastructure if advanced transmission technologies are not deployed.
(d) In any integrated resource plan filed with the commission under 170 IAC 4-7 after December 31, 2029, an electric utility must include a description of the electric utility's transmission and distribution systems, as applicable, as specified by the commission under 170 IAC 4-7.
As added by P.L.10-2025, SEC.1.
Status: in_force · Read it on the official government site
Need a lawyer in Indiana?
Find a Indiana lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.