Commission's review of petition; considerations; impact of federal phaseout mandates; provision of service with attributes specified in state policy; use of surplus interconnection service
Official statutory text
Sec. 4. (a) As used in this section, "federal phaseout mandate" means any federal statutory or regulatory requirement that:
(1) is established after April 20, 2021, by the Congress of the United States, a federal regulatory agency, or a federal executive order; and
(2) requires the phaseout or discontinuance of a particular type of electric generating facility, technology, or fuel source.
(b) As used in this section, "surplus interconnection service" has the meaning set forth in section 3.6 of this chapter.
(c) In acting upon any petition for the construction, purchase, or lease of any facility for the generation of electricity, the commission shall take into account the following:
(1) The applicant's current and potential arrangement with other electric utilities for:
(A) the interchange of power;
(B) the pooling of facilities;
(C) the purchase of power; and
(D) joint ownership of facilities.
(2) Other methods for providing reliable, efficient, and economical electric service, including the refurbishment of existing facilities, conservation, load management, cogeneration, and renewable energy sources.
(3) With respect to a petition that:
(A) is for the construction of a new generating facility; and
(B) is submitted to the commission after June 30, 2021, and before January 1, 2025;
the impact of federal phaseout mandates on the estimated useful life of each proposed generating facility included in the petition, including depreciation expense associated with each facility.
(4) With respect to a petition that is submitted to the commission after June 30, 2023, whether the proposed construction, purchase, or lease of the facility will result in the provision of electric utility service with the attributes set forth in IC 8-1-2-0.6, including:
(A) reliability;
(B) affordability;
(C) resiliency;
(D) stability; and
(E) environmental sustainability;
as described in IC 8-1-2-0.6.
(5) With respect to a petition that is submitted to the commission after December 31, 2029, whether:
(A) the petitioner has conducted an analysis, as part of an integrated resource plan in accordance with section 3.6 of this chapter or otherwise, of the use of surplus interconnection service as an alternative to, or in conjunction with, the proposed construction, purchase, or lease of the facility; and
(B) the proposed construction, use, or lease of the facility will make use of, or allow for the use of, surplus interconnection service.
As added by P.L.43-1983, SEC.12. Amended by P.L.88-1985, SEC.9; P.L.180-2021, SEC.3; P.L.55-2023, SEC.4; P.L.126-2026, SEC.2.
(1) is established after April 20, 2021, by the Congress of the United States, a federal regulatory agency, or a federal executive order; and
(2) requires the phaseout or discontinuance of a particular type of electric generating facility, technology, or fuel source.
(b) As used in this section, "surplus interconnection service" has the meaning set forth in section 3.6 of this chapter.
(c) In acting upon any petition for the construction, purchase, or lease of any facility for the generation of electricity, the commission shall take into account the following:
(1) The applicant's current and potential arrangement with other electric utilities for:
(A) the interchange of power;
(B) the pooling of facilities;
(C) the purchase of power; and
(D) joint ownership of facilities.
(2) Other methods for providing reliable, efficient, and economical electric service, including the refurbishment of existing facilities, conservation, load management, cogeneration, and renewable energy sources.
(3) With respect to a petition that:
(A) is for the construction of a new generating facility; and
(B) is submitted to the commission after June 30, 2021, and before January 1, 2025;
the impact of federal phaseout mandates on the estimated useful life of each proposed generating facility included in the petition, including depreciation expense associated with each facility.
(4) With respect to a petition that is submitted to the commission after June 30, 2023, whether the proposed construction, purchase, or lease of the facility will result in the provision of electric utility service with the attributes set forth in IC 8-1-2-0.6, including:
(A) reliability;
(B) affordability;
(C) resiliency;
(D) stability; and
(E) environmental sustainability;
as described in IC 8-1-2-0.6.
(5) With respect to a petition that is submitted to the commission after December 31, 2029, whether:
(A) the petitioner has conducted an analysis, as part of an integrated resource plan in accordance with section 3.6 of this chapter or otherwise, of the use of surplus interconnection service as an alternative to, or in conjunction with, the proposed construction, purchase, or lease of the facility; and
(B) the proposed construction, use, or lease of the facility will make use of, or allow for the use of, surplus interconnection service.
As added by P.L.43-1983, SEC.12. Amended by P.L.88-1985, SEC.9; P.L.180-2021, SEC.3; P.L.55-2023, SEC.4; P.L.126-2026, SEC.2.
Status: in_force · Read it on the official government site
Need a lawyer in Indiana?
Find a Indiana lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.