Ind. Code § 8-1-8.5-6
This is the official text of Ind. Code § 8-1-8.5-6, part of Indiana’s Code — part of the compiled statutory law of Indiana, published by the state as "Code." Browse the sections below, each linked to its official government source.
Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.
Review of construction; force and effect of certificate approved under review; election to defer review
Official statutory text
Sec. 6. (a) In addition to the review of the continuing need for the facility under construction prescribed in section 5.5 of this chapter, the commission shall, at the request of the public utility, maintain an ongoing review of such construction as it proceeds. The applicant shall submit each year during construction, or at such other periods as the commission and the public utility mutually agree, a progress report and any revisions in the cost estimates for the construction.
(b) If the commission approves the construction and the cost of the portion of the facility under review, the certificate shall remain in full force and effect.
(c) If the commission disapproves of all or part of the construction or cost of the portion of the facility under review, the commission may modify or revoke the certificate.
(d) Alternatively, the public utility may elect to forego commission review under subsection (a) and defer the review of the construction and cost until completion or cancellation of the facility.
As added by P.L.43-1983, SEC.12. Amended by P.L.88-1985, SEC.12; P.L.53-1992, SEC.6.
(b) If the commission approves the construction and the cost of the portion of the facility under review, the certificate shall remain in full force and effect.
(c) If the commission disapproves of all or part of the construction or cost of the portion of the facility under review, the commission may modify or revoke the certificate.
(d) Alternatively, the public utility may elect to forego commission review under subsection (a) and defer the review of the construction and cost until completion or cancellation of the facility.
As added by P.L.43-1983, SEC.12. Amended by P.L.88-1985, SEC.12; P.L.53-1992, SEC.6.
Status: in_force · Read it on the official government site
Need a lawyer in Indiana?
Find a Indiana lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.