Md. Code, State Finance and Procurement § 15-108
This is the official text of Md. Code, State Finance and Procurement § 15-108, part of Maryland’s Code, State Finance and Procurement — governs the state budget and government contracting.
Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.
§15–108.
Official statutory text
(a) This section does not apply to any procurement contract funded with tax-exempt financing.
(b) (1) Subject to the requirements of this section, a contractor under a procurement contract that a unit awards for construction is entitled to have retainage under the procurement contract placed in an escrow account if the contractor:
(i) elects that procedure in the procurement contract in the space provided for that election; and
(ii) submits to the unit an escrow agreement that meets the requirements of subsection (c) of this section.
(2) The procurement contract shall identify the escrow agent.
(c) The escrow agreement shall:
(1) be on a form that the unit provides;
(2) include the complete address of both the escrow agent and the surety;
(3) authorize the unit to pay retainage to the escrow agent; and
(4) be signed by:
(i) the contractor;
(ii) the surety for the contractor; and
(iii) the escrow agent.
(d) On compliance with the requirements of subsection (b) of this section, the unit shall pay the retainage to the escrow agent unless:
(1) federal money is involved and application of this section would jeopardize timely recovery of that federal money; or
(2) retainage is withheld for:
(i) lack of progress on the part of the contractor; or
(ii) other violations by the contractor.
(e) In accordance with the escrow agreement, a contractor may require an escrow agent:
(1) to invest the retainage placed in the escrow account; and
(2) to the extent the contractor is entitled to retainage under subsection (f)(2)(ii) of this section, to pay the earnings on the investment to the contractor.
(f) (1) Retainage may be released to the contractor only as directed by the unit.
(2) At the time of final payment, the unit shall direct the escrow agent to settle the escrow account by distributing money in the escrow account in the following order:
(i) to the unit for any claim it may have against the contractor under the procurement contract;
(ii) unless waived by the Board, to the Comptroller for any claim exceeding $50 against the contractor by the State, a unit, or a State controlled governmental entity; and
(iii) to the contractor.
(b) (1) Subject to the requirements of this section, a contractor under a procurement contract that a unit awards for construction is entitled to have retainage under the procurement contract placed in an escrow account if the contractor:
(i) elects that procedure in the procurement contract in the space provided for that election; and
(ii) submits to the unit an escrow agreement that meets the requirements of subsection (c) of this section.
(2) The procurement contract shall identify the escrow agent.
(c) The escrow agreement shall:
(1) be on a form that the unit provides;
(2) include the complete address of both the escrow agent and the surety;
(3) authorize the unit to pay retainage to the escrow agent; and
(4) be signed by:
(i) the contractor;
(ii) the surety for the contractor; and
(iii) the escrow agent.
(d) On compliance with the requirements of subsection (b) of this section, the unit shall pay the retainage to the escrow agent unless:
(1) federal money is involved and application of this section would jeopardize timely recovery of that federal money; or
(2) retainage is withheld for:
(i) lack of progress on the part of the contractor; or
(ii) other violations by the contractor.
(e) In accordance with the escrow agreement, a contractor may require an escrow agent:
(1) to invest the retainage placed in the escrow account; and
(2) to the extent the contractor is entitled to retainage under subsection (f)(2)(ii) of this section, to pay the earnings on the investment to the contractor.
(f) (1) Retainage may be released to the contractor only as directed by the unit.
(2) At the time of final payment, the unit shall direct the escrow agent to settle the escrow account by distributing money in the escrow account in the following order:
(i) to the unit for any claim it may have against the contractor under the procurement contract;
(ii) unless waived by the Board, to the Comptroller for any claim exceeding $50 against the contractor by the State, a unit, or a State controlled governmental entity; and
(iii) to the contractor.
Status: in_force · Read it on the official government site
Need a lawyer in Maryland?
Find a Maryland lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.