Mo. Rev. Stat. § 8.962
This is the official text of Mo. Rev. Stat. § 8.962, part of Missouri’s Rev. Stat — part of the compiled statutory law of Missouri, published by the state as "Rev. Stat." Browse the sections below, each linked to its official government source.
Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.
8.962 Public works contract defined — certain contract clauses against public ...
Official statutory text
8.962. Public works contract defined — certain contract clauses against public policy, exceptions. — 1. As used in this section, the term "public works contract" means a contract of the state, county, city and other political subdivisions of the state, except the Missouri transportation department, for the construction, alteration, repair, or maintenance of any building, structure, highway, bridge, viaduct, pipeline, public works, or any other works dealing with construction, which shall include, but need not be limited to, moving, demolition, or excavation performed in conjunction with such work.
2. Any clause in a public works contract that purports to waive, release, or extinguish the rights of a contractor to recover costs or damages, or obtain an equitable adjustment, for delays in performing such contract, if such delay is caused in whole, or in part, by acts or omissions within the control of the contracting public entity or persons acting on behalf thereof, is against public policy and is void and unenforceable.
3. Subsection 2 of this section is not intended to render void any contract provision of a public works contract that:
(1) Precludes a contractor from recovering that portion of delay costs caused by the acts or omissions of the contractor or its agents;
(2) Requires notice of any delay by the party responsible for such delay;
(3) Provides for reasonable liquidated damages; or
(4) Provides for arbitration or any other procedure designed to settle contract disputes.
(L. 2022 S.B. 758) Transferred 2022; formerly § 34.058 .
2. Any clause in a public works contract that purports to waive, release, or extinguish the rights of a contractor to recover costs or damages, or obtain an equitable adjustment, for delays in performing such contract, if such delay is caused in whole, or in part, by acts or omissions within the control of the contracting public entity or persons acting on behalf thereof, is against public policy and is void and unenforceable.
3. Subsection 2 of this section is not intended to render void any contract provision of a public works contract that:
(1) Precludes a contractor from recovering that portion of delay costs caused by the acts or omissions of the contractor or its agents;
(2) Requires notice of any delay by the party responsible for such delay;
(3) Provides for reasonable liquidated damages; or
(4) Provides for arbitration or any other procedure designed to settle contract disputes.
(L. 2022 S.B. 758) Transferred 2022; formerly § 34.058 .
Status: in_force · Read it on the official government site
Need a lawyer in Missouri?
Find a Missouri lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.