28-2-2104 Obligations upon delay of payment
Official statutory text
28-2-2104 . Obligations upon delay of payment. (1) If a periodic or final payment that is required by a construction contract to be paid by an owner to a contractor is delayed by more than 30 days from the date the payment is required by the contract to be made, the owner shall pay to the contractor interest, beginning on the day following the date when the payment is due, at the rate of 1 1/2% a month or a pro rata fraction of that amount on the unpaid balance. If the contractor receives interest from the owner for a delayed payment by the owner, the contractor shall ensure that any interest accrued on a delayed payment is distributed by the contractor to subcontractors on a pro rata basis.
(2) If a periodic or final payment required by a subcontract to be paid by a contractor to a subcontractor is delayed for more than 30 days from the date the payment is required by the subcontract to be made, the contractor shall pay to the subcontractor interest beginning on the day following the date when the payment is due, at the rate of 1 1/2% a month or a pro rata fraction of that amount on the unpaid balance. If a subcontractor receives interest from the contractor for a delayed payment by the contractor, the subcontractor shall ensure that any interest accrued on the delayed payment is distributed by the subcontractor to other subcontractors, if any, on a pro rata basis.
(3) Acceptance of the final payment releases any claim for interest on the payment.
(2) If a periodic or final payment required by a subcontract to be paid by a contractor to a subcontractor is delayed for more than 30 days from the date the payment is required by the subcontract to be made, the contractor shall pay to the subcontractor interest beginning on the day following the date when the payment is due, at the rate of 1 1/2% a month or a pro rata fraction of that amount on the unpaid balance. If a subcontractor receives interest from the contractor for a delayed payment by the contractor, the subcontractor shall ensure that any interest accrued on the delayed payment is distributed by the subcontractor to other subcontractors, if any, on a pro rata basis.
(3) Acceptance of the final payment releases any claim for interest on the payment.
Status: in_force · Read it on the official government site
Need a lawyer in Montana?
Find a Montana lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.