60-2-115 Contract let by commission -- time for final payment of contract price -- interest -- definitions
Official statutory text
60-2-115 . Contract let by commission -- time for final payment of contract price -- interest -- definitions. (1) Subject to subsections (2) through (4), the department shall comply with the 30-day time period for payment of contracts as provided in 18-2-306 for all contracts let by the commission in accordance with this part.
(2) For the final payment on a contract, the department shall, within 30 days after a request by the contractor for final acceptance, perform an inspection of the project and notify the contractor of whether the department has granted or refused final acceptance.
(3) If the department notifies the contractor that the department has granted final acceptance, the department shall make the final payment of the contract price specified in the contract to the other party to the contract within 90 days after the notice.
(4) (a) If the department notifies the contractor that the department has refused final acceptance, the department shall include with the notice a list of all deficiencies that must be cured before the department will grant final acceptance.
(b) After the contractor has cured all of the deficiencies, the contractor shall request final acceptance by the department. Within 30 days after the contractor's request, the department shall perform an inspection of all of the cured deficiencies.
(c) If the department notifies the contractor of its final acceptance, the department shall make the final payment as provided in subsection (3).
(d) If the department notifies the contractor that the department has refused final acceptance, the department shall:
(i) notify the contractor of any remaining deficiencies; and
(ii) grant final acceptance, subject to any remedy provided under the provisions of Title 28, chapter 2.
(5) When the department grants final acceptance, the department shall immediately consider the contract complete and close the contract.
(6) As used in this section, the following definitions apply:
(a) "Final acceptance" means the department's acceptance of the construction, maintenance, or public works project upon certification by the architect, project engineer, or other representative of the department of final completion of the project.
(b) "Final completion" means that the project has been completed in accordance with the terms and conditions of the contract documents and all warranties have expired.
(2) For the final payment on a contract, the department shall, within 30 days after a request by the contractor for final acceptance, perform an inspection of the project and notify the contractor of whether the department has granted or refused final acceptance.
(3) If the department notifies the contractor that the department has granted final acceptance, the department shall make the final payment of the contract price specified in the contract to the other party to the contract within 90 days after the notice.
(4) (a) If the department notifies the contractor that the department has refused final acceptance, the department shall include with the notice a list of all deficiencies that must be cured before the department will grant final acceptance.
(b) After the contractor has cured all of the deficiencies, the contractor shall request final acceptance by the department. Within 30 days after the contractor's request, the department shall perform an inspection of all of the cured deficiencies.
(c) If the department notifies the contractor of its final acceptance, the department shall make the final payment as provided in subsection (3).
(d) If the department notifies the contractor that the department has refused final acceptance, the department shall:
(i) notify the contractor of any remaining deficiencies; and
(ii) grant final acceptance, subject to any remedy provided under the provisions of Title 28, chapter 2.
(5) When the department grants final acceptance, the department shall immediately consider the contract complete and close the contract.
(6) As used in this section, the following definitions apply:
(a) "Final acceptance" means the department's acceptance of the construction, maintenance, or public works project upon certification by the architect, project engineer, or other representative of the department of final completion of the project.
(b) "Final completion" means that the project has been completed in accordance with the terms and conditions of the contract documents and all warranties have expired.
Status: in_force · Read it on the official government site
Need a lawyer in Montana?
Find a Montana lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.