Defect in new residence: Duty to repair; deadline for repair; extensions; disciplinary action for failure to comply
Official statutory text
Except as otherwise provided in NRS 40.670 , if a contractor, subcontractor, supplier or design professional receives written notice of a constructional defect not more than 1 year after the close of escrow of the initial purchase of the residence, the contractor, subcontractor, supplier or design professional shall make the repairs within 45 days after receiving the written notice unless completion is delayed by the claimant or by other events beyond the control of the contractor, subcontractor, supplier or design professional, or timely completion of repairs is not reasonably possible. The contractor, subcontractor, supplier or design professional and claimant may agree in writing to extend the period prescribed by this section. If a contractor or subcontractor fails to comply with this section, the contractor or subcontractor is immediately subject to discipline pursuant to NRS 624.300 .
Status: in_force · Read it on the official government site
Need a lawyer in Nevada?
Find a Nevada lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.