66 Pa.C.S. § 514

This is the official text of 66 Pa.C.S. § 514, part of Pennsylvania’s Pa.C.S — part of the compiled statutory law of Pennsylvania, published by the state as "Pa.C.S." Browse the sections below, each linked to its official government source.

Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.

Use of coal.

Official statutory text

(a) Upgrading capability to use coal.--The commission shall promulgate regulations which require utilities to uprate their electric power production by increasing the capability to use coal in existing coal-fueled plants where economically feasible and where the uprate is beneficial to ratepayers.

(b) Incentive for uprating.--The commission shall promulgate regulations which establish a special cost recovery and shared benefits procedure for electric utilities and their ratepayers as an incentive to implement upratings as provided in subsection

(a). Nothing in this section shall permit or require the commission to establish rates or procedures which are inconsistent with any other section in this title.

(c) Cost of upgrading.--Notwithstanding section 1315 (relating to limitation on consideration of certain costs for electric utilities) and subject to regulations promulgated by the commission, the commission may allow a portion of the prudently incurred costs, determined on a per megawatt basis and not to exceed 50% of the unit's undepreciated original cost per megawatt, of uprating the capability of an existing coal-fueled plant to use coal mined in Pennsylvania to be made a part of the rate base or otherwise included in the rates charged by the utility before such uprating is completed. This subsection shall not apply unless, upon application of the

affected public utility, the commission determines that the uprating would be more cost effective for the utility's ratepayers than other alternatives for meeting the utility's load and capacity requirements. Notwithstanding section 1309 (relating to rates fixed on complaint; investigation of costs of production), the commission, by regulation, shall provide for a utility to remove the costs of an uprating from its rate base and to refund any revenues collected as the result of this subsection, plus interest, which shall be the average rate of interest specified for residential mortgage lending by the Secretary of Banking in accordance with the act of January 30, 1974 (P.L.13, No.6), referred to as the Loan Interest and Protection Law, during the period or periods for which the commission orders refunds, if the commission, after notice and hearings, determines that the uprating has not been completed within a reasonable time. (May 31, 1984, P.L.370, No.74, eff. 60 days; Dec. 21, 1984, P.L.1265, No.240, eff. imd.; July 3, 1986, P.L.348, No.80, eff. 60 days) References in Text. The Secretary of Banking, referred to in subsec. (c), was renamed the Secretary of Banking and Securities by the act of July 2, 2012 (P.L.814, No.86). Cross References. Section 514 is referred to in section 523 of this title.

Status: in_force · Read it on the official government site

Need a lawyer in Pennsylvania?

Find a Pennsylvania lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.