S.D. Codified Laws § 46A-1-94
This is the official text of S.D. Codified Laws § 46A-1-94, part of South Dakota’s Codified Laws — part of the compiled statutory law of South Dakota, published by the state as "Codified Laws." Browse the sections below, each linked to its official government source.
Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.
Perkins County rural water system
Official statutory text
Pursuant to §§ 46A-1-11 to 46A-1-13 , inclusive, construction of a twenty-seven million nine hundred ninety-nine thousand two hundred fifty dollar Perkins County rural water system as generally described in the report, Final Engineering Report, for Perkins County Rural Water System Inc., Bison, South Dakota, dated January 2003, is hereby authorized for the purpose of providing safe and adequate municipal, rural, and industrial water supplies in Perkins County.
The Legislature finds that it is in the best interest of the Perkins County rural water system to provide a portion of the nonfederal matching requirements as enumerated in P.L. 106-136 as amended to January 1, 2011, through the state water resources management system revolving loan program. The Board of Water and Natural Resources may provide loans under the state water resources management system revolving loan program in amounts not to exceed a total of four million five hundred thousand dollars to the Perkins County rural water system to provide a portion of the nonfederal matching requirements as enumerated in P.L. 106-136 as amended to January 1, 2011. No disbursements may be made under the loans authorized by this section unless funds are appropriated by the Legislature in conformance with § 46A-1-61 .
Notwithstanding the provisions of § 46A-1-66 , no interest may accrue until the Board of Water and Natural Resources certifies the completion of the construction of the project as authorized. The initial loan repayment is due and payable one year following the certification of construction completion. Loan terms and conditions shall be set by the Board of Water and Natural Resources.
The Board of Water and Natural Resources may provide grants in amounts not to exceed two million five hundred thousand dollars, or so much thereof as may be necessary, to the Perkins County rural water system project to provide the State of South Dakota's portion of the nonfederal matching requirements for the project. No disbursements may be made under the grant authorized by this section unless funds are appropriated by the Legislature in conformance with § 46A-1-61 .
The loan and grant authorized by this section may be increased or decreased by such amounts as may be justified by reason of ordinary fluctuations in development costs incurred after January 1, 2001, as indicated by engineering costs indices applicable for the type of construction involved.
Source: SL 1996, ch 265, § 11; SL 2004, ch 52, § 5, eff. Feb. 25, 2004; SL 2011, ch 165, § 310.
The Legislature finds that it is in the best interest of the Perkins County rural water system to provide a portion of the nonfederal matching requirements as enumerated in P.L. 106-136 as amended to January 1, 2011, through the state water resources management system revolving loan program. The Board of Water and Natural Resources may provide loans under the state water resources management system revolving loan program in amounts not to exceed a total of four million five hundred thousand dollars to the Perkins County rural water system to provide a portion of the nonfederal matching requirements as enumerated in P.L. 106-136 as amended to January 1, 2011. No disbursements may be made under the loans authorized by this section unless funds are appropriated by the Legislature in conformance with § 46A-1-61 .
Notwithstanding the provisions of § 46A-1-66 , no interest may accrue until the Board of Water and Natural Resources certifies the completion of the construction of the project as authorized. The initial loan repayment is due and payable one year following the certification of construction completion. Loan terms and conditions shall be set by the Board of Water and Natural Resources.
The Board of Water and Natural Resources may provide grants in amounts not to exceed two million five hundred thousand dollars, or so much thereof as may be necessary, to the Perkins County rural water system project to provide the State of South Dakota's portion of the nonfederal matching requirements for the project. No disbursements may be made under the grant authorized by this section unless funds are appropriated by the Legislature in conformance with § 46A-1-61 .
The loan and grant authorized by this section may be increased or decreased by such amounts as may be justified by reason of ordinary fluctuations in development costs incurred after January 1, 2001, as indicated by engineering costs indices applicable for the type of construction involved.
Source: SL 1996, ch 265, § 11; SL 2004, ch 52, § 5, eff. Feb. 25, 2004; SL 2011, ch 165, § 310.
Status: in_force · Read it on the official government site
Need a lawyer in South Dakota?
Find a South Dakota lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.