§ 104.107. RATE SUSPENSION; DEADLINE.

Official statutory text

(a) Pending the hearing and a decision:

(1) the local regulatory authority, after delivering to the gas utility a written statement of the regulatory authority's reasons, may suspend the operation of the schedule for not longer than 90 days after the date the schedule would otherwise be effective; and

(2) the railroad commission may suspend the operation of the schedule for not longer than 150 days after the date the schedule would otherwise be effective.

(b) The 150-day period prescribed by Subsection (a)(2) shall be extended for two days for each day the actual hearing on the merits of the case exceeds 15 days.

(c) If the regulatory authority does not make a final determination concerning a schedule of rates before expiration of the applicable suspension period, the regulatory authority is considered to have approved the schedule. This approval is subject to the authority of the regulatory authority thereafter to continue a hearing in progress.

Status: in_force · Read it on the official government site

Need a lawyer in Texas?

Find a Texas lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.