§ 38.078. CIRCUIT SEGMENTATION STUDY AND COST RECOVERY.
Official statutory text
(a) Not later than September 15, 2023, the commission shall direct each transmission and distribution utility to perform a circuit segmentation study.
(b) A circuit segmentation study must:
(1) use an engineering analysis to examine whether and how the transmission and distribution utility's transmission and distribution systems can be segmented and sectionalized to manage and rotate outages more evenly across all customers and circuits, while maintaining the protections offered to critical facilities;
(2) include an engineering analysis of the feasibility of using sectionalization, automated reclosers, and other technology to break up the circuits that host significant numbers of critical facilities into smaller segments for outage management purposes to enable more granular and flexible outage management;
(3) identify feeders with critical facilities that, if equipped with facility-specific backup power systems and segmentation, can enhance the utility's outage management flexibility; and
(4) include an estimate of the time, capital cost, and expected improvements to load-shed management associated with the circuit segmentation study.
(c) Each transmission and distribution utility shall submit a report of the conclusions of the utility's study to the commission not later than September 1, 2024.
(d) The commission shall review each circuit segmentation study not later than March 15, 2025.
(b) A circuit segmentation study must:
(1) use an engineering analysis to examine whether and how the transmission and distribution utility's transmission and distribution systems can be segmented and sectionalized to manage and rotate outages more evenly across all customers and circuits, while maintaining the protections offered to critical facilities;
(2) include an engineering analysis of the feasibility of using sectionalization, automated reclosers, and other technology to break up the circuits that host significant numbers of critical facilities into smaller segments for outage management purposes to enable more granular and flexible outage management;
(3) identify feeders with critical facilities that, if equipped with facility-specific backup power systems and segmentation, can enhance the utility's outage management flexibility; and
(4) include an estimate of the time, capital cost, and expected improvements to load-shed management associated with the circuit segmentation study.
(c) Each transmission and distribution utility shall submit a report of the conclusions of the utility's study to the commission not later than September 1, 2024.
(d) The commission shall review each circuit segmentation study not later than March 15, 2025.
Status: in_force · Read it on the official government site
Need a lawyer in Texas?
Find a Texas lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.