§ 251. Areas served by several companies
Official statutory text
(a) In any area that two or more companies distributing electrical energy are authorized to serve, a company shall not construct or extend its facilities, or furnish or offer to furnish its service to any person or property presently served by another public utility, without the written consent of the other public utility or unless the Public Utility Commission, after notice and hearing, finds and determines that the service rendered by the serving public utility is inadequate and is not likely to be made adequate.
(b) In the event service is requested for premises in an area that two or more companies distributing electrical energy are authorized to serve and have facilities available for service to the property, the public utility company the existing service facilities of which are nearest the metering point on the premises to be served shall, subject to the other applicable provisions of this section, be entitled to serve the premise.
(c) In the event that service is requested for premises not within the service territory of any company, and if more than one other public utility is available for service to the property, the public utility whose existing service facilities are nearest the metering point on the premises to be served shall, subject to the other applicable provisions of this section, be entitled to serve said premises.
(d) A company shall not construct or extend its facilities or furnish or offer to furnish its services to premises within the service territory of another company without being requested to do so by the company in whose territory the premises are located or unless the Public Utility Commission, upon petition of the person served or to be served, after notice and hearing, finds and determines that the service rendered by such public utility in whose territory and premises are located is inadequate and will not be likely to be made adequate.
(e) In resolving any dispute under subsections (b), (c), and (d) of this section, the Commission shall consider the factors set forth in section 249 of this title.
(b) In the event service is requested for premises in an area that two or more companies distributing electrical energy are authorized to serve and have facilities available for service to the property, the public utility company the existing service facilities of which are nearest the metering point on the premises to be served shall, subject to the other applicable provisions of this section, be entitled to serve the premise.
(c) In the event that service is requested for premises not within the service territory of any company, and if more than one other public utility is available for service to the property, the public utility whose existing service facilities are nearest the metering point on the premises to be served shall, subject to the other applicable provisions of this section, be entitled to serve said premises.
(d) A company shall not construct or extend its facilities or furnish or offer to furnish its services to premises within the service territory of another company without being requested to do so by the company in whose territory the premises are located or unless the Public Utility Commission, upon petition of the person served or to be served, after notice and hearing, finds and determines that the service rendered by such public utility in whose territory and premises are located is inadequate and will not be likely to be made adequate.
(e) In resolving any dispute under subsections (b), (c), and (d) of this section, the Commission shall consider the factors set forth in section 249 of this title.
Status: in_force · Read it on the official government site
Need a lawyer in Vermont?
Find a Vermont lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.