Va. Code Ann. § 2.2-1133
This is the official text of Va. Code Ann. § 2.2-1133, part of Virginia’s Code of Virginia — the complete compiled statutory law of Virginia, organized into 60+ numbered titles by subject.
Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.
Use of value engineering
Official statutory text
A. The Division shall ensure that value engineering is employed for any capital project costing more than $5 million. Value engineering may also be used for any project costing $5 million or less. For purposes of this section, "value engineering" means a systematic process of review and analysis of a capital project by a team of persons not originally involved in the project. Such team, which shall include appropriate professionals licensed in accordance with Chapter 4 (§ 54.1-400 et seq.) of Title 54.1, may offer suggestions that would improve project quality and reduce total project cost by combining or eliminating inefficient or expensive parts or steps in the original proposal or by totally redesigning the project using different technologies, materials, or methods.
B. The review developed pursuant to subsection A shall be compiled in a value engineering report and submitted to the Division. Each item included in the value engineering report shall have a status designation of accepted, declined, or accepted as modified. The Division, within 45 days, must approve the value engineering report before the project may move to the next phase of design.
C. A value engineering report shall not be required for projects that (i) are designed utilizing either the design-build or construction management at risk basis and (ii) have the value engineering process as an integral component. In such cases, a written summary of the cost savings that have been incorporated into the design shall be provided to the Division prior to moving forward to the construction phase of the contract.
D. The Director of the Department may waive the requirements of this section for any proposed capital project for compelling reasons. Any waiver shall be in writing, state the reasons for the waiver, and apply only to a single capital project. On or before September 15 of each year, the Director of the Department shall report to the Governor and the General Assembly on the (i) number and value of the capital projects where value engineering was employed and (ii) identity of the capital projects for which a waiver of the requirements of this section was granted, including a statement of the compelling reasons for granting the waiver. The report shall cover projects completed or for which a waiver was granted within the previous fiscal year.
E. Notwithstanding any law to the contrary, the provisions of this section shall apply to public institutions of higher education in the Commonwealth.
1994, cc. 442 , 829 , § 2.1-483.1:1; 1996, c. 553 ; 1997, c. 230 ; 1998, c. 207 ; 2001, c. 844 ; 2008, c. 370 ; 2015, c. 572 .
B. The review developed pursuant to subsection A shall be compiled in a value engineering report and submitted to the Division. Each item included in the value engineering report shall have a status designation of accepted, declined, or accepted as modified. The Division, within 45 days, must approve the value engineering report before the project may move to the next phase of design.
C. A value engineering report shall not be required for projects that (i) are designed utilizing either the design-build or construction management at risk basis and (ii) have the value engineering process as an integral component. In such cases, a written summary of the cost savings that have been incorporated into the design shall be provided to the Division prior to moving forward to the construction phase of the contract.
D. The Director of the Department may waive the requirements of this section for any proposed capital project for compelling reasons. Any waiver shall be in writing, state the reasons for the waiver, and apply only to a single capital project. On or before September 15 of each year, the Director of the Department shall report to the Governor and the General Assembly on the (i) number and value of the capital projects where value engineering was employed and (ii) identity of the capital projects for which a waiver of the requirements of this section was granted, including a statement of the compelling reasons for granting the waiver. The report shall cover projects completed or for which a waiver was granted within the previous fiscal year.
E. Notwithstanding any law to the contrary, the provisions of this section shall apply to public institutions of higher education in the Commonwealth.
1994, cc. 442 , 829 , § 2.1-483.1:1; 1996, c. 553 ; 1997, c. 230 ; 1998, c. 207 ; 2001, c. 844 ; 2008, c. 370 ; 2015, c. 572 .
Status: in_force · Read it on the official government site
Need a lawyer in Virginia?
Find a Virginia lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.