Deposit of certain retained funds on certain contracts with local governments; penalty for failure to timely complete
Official statutory text
A. Any county, city, town or agency thereof or other political subdivision of the Commonwealth when contracting directly with contractors for public contracts of $200,000 or more for construction of highways, roads, streets, bridges, parking lots, demolition, clearing, grading, excavating, paving, pile driving, miscellaneous drainage structures, and the installation of water, gas, sewer lines and pumping stations where portions of the contract price are to be retained, shall include in the Bid Proposal an option for the contractor to use an escrow account procedure for utilization of the political subdivision's retainage funds by so indicating in the space provided in the proposal documents. In the event the contractor elects to use the escrow account procedure, the escrow agreement form included in the Bid Proposal and Contract shall be executed and submitted to the political subdivision within fifteen calendar days after notification. If the escrow agreement form is not submitted within the fifteen-day period, the contractor shall forfeit his rights to the use of the escrow account procedure.
B. In order to have retained funds paid to an escrow agent, the contractor, the escrow agent, and the surety shall execute an escrow agreement form. The contractor's escrow agent shall be a trust company, bank or savings institution with its principal office located in the Commonwealth. The escrow agreement and all regulations adopted by the political subdivision entering into the contract shall be substantially the same as that used by the Virginia Department of Transportation.
C. This section shall not apply to public contracts for construction for railroads, public transit systems, runways, dams, foundations, installation or maintenance of power systems for the generation and primary and secondary distribution of electric current ahead of the customer's meter, the installation or maintenance of telephone, telegraph or signal systems for public utilities and the construction or maintenance of solid waste or recycling facilities and treatment plants.
D. Any such public contract for construction with a county, city, town or agency thereof or other political subdivision of the Commonwealth, which includes payment of interest on retained funds, may require a provision whereby the contractor, exclusive of reasonable circumstances beyond the control of the contractor stated in the contract, shall pay a specified penalty for each day exceeding the completion date stated in the contract.
E. Any subcontract for such public project that provides for similar progress payments shall be subject to the provisions of this section.
1989, c. 1, § 11-56.1; 2001, c. 844 .
B. In order to have retained funds paid to an escrow agent, the contractor, the escrow agent, and the surety shall execute an escrow agreement form. The contractor's escrow agent shall be a trust company, bank or savings institution with its principal office located in the Commonwealth. The escrow agreement and all regulations adopted by the political subdivision entering into the contract shall be substantially the same as that used by the Virginia Department of Transportation.
C. This section shall not apply to public contracts for construction for railroads, public transit systems, runways, dams, foundations, installation or maintenance of power systems for the generation and primary and secondary distribution of electric current ahead of the customer's meter, the installation or maintenance of telephone, telegraph or signal systems for public utilities and the construction or maintenance of solid waste or recycling facilities and treatment plants.
D. Any such public contract for construction with a county, city, town or agency thereof or other political subdivision of the Commonwealth, which includes payment of interest on retained funds, may require a provision whereby the contractor, exclusive of reasonable circumstances beyond the control of the contractor stated in the contract, shall pay a specified penalty for each day exceeding the completion date stated in the contract.
E. Any subcontract for such public project that provides for similar progress payments shall be subject to the provisions of this section.
1989, c. 1, § 11-56.1; 2001, c. 844 .
Status: in_force · Read it on the official government site
Need a lawyer in Virginia?
Find a Virginia lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.