Ark. Code Ann. § 23-4-408

This is the official text of Ark. Code Ann. § 23-4-408, part of Arkansas’s Code Ann — part of the compiled statutory law of Arkansas, published by the state as "Code Ann." Browse the sections below, each linked to its official government source.

Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.

Interim implementation of suspended rates

Official statutory text

(a) If the public utility contends that an immediate and impelling necessity exists for the requested rate increase, a petition may be filed with the Arkansas Public Service Commission narrating the alleged circumstances and requesting a hearing on the petition. (b) The hearing must commence within thirty (30) days from the date of the filing of the petition or at such subsequent time as may be mutually agreeable to the commission and the utility. (c) If the commission finds at the hearing that there is substantial merit to the allegation of the utility's claims, the commission may permit all or a portion of the rate to become effective if there is filed with the commission a bond to be approved by it, payable to the State of Arkansas in such amount and with such sufficient security to insure the prompt payment of any damages or refunds, with interest, to the persons entitled thereto if the rate so put into effect is finally determined to be excessive or if there is substituted for the bond other arrangements satisfactory to the commission for the protection of the parties interested. (d) The findings of the commission relative to the petition of the utility for the immediate and impelling necessity for relief shall be issued on or before the sixtieth day following the date of filing of the petition. Acts 1935, No. 324, § 18; Pope's Dig., § 2081; Acts 1955, No. 31, § 1; 1975 (Extended Sess., 1976), No. 1181, § 1; 1980 (2nd Ex. Sess.), No. 4, § 1; 1981 (Ex. Sess.), No. 30, § 1; 1985, No. 523, § 1; A.S.A. 1947, § 73-217; reen. Acts 1987, No. 994, § 1.

(a) If the public utility contends that an immediate and impelling necessity exists for the requested rate increase, a petition may be filed with the Arkansas Public Service Commission narrating the alleged circumstances and requesting a hearing on the petition.

(b) The hearing must commence within thirty (30) days from the date of the filing of the petition or at such subsequent time as may be mutually agreeable to the commission and the utility.

(c) If the commission finds at the hearing that there is substantial merit to the allegation of the utility's claims, the commission may permit all or a portion of the rate to become effective if there is filed with the commission a bond to be approved by it, payable to the State of Arkansas in such amount and with such sufficient security to insure the prompt payment of any damages or refunds, with interest, to the persons entitled thereto if the rate so put into effect is finally determined to be excessive or if there is substituted for the bond other arrangements satisfactory to the commission for the protection of the parties interested.

(d) The findings of the commission relative to the petition of the utility for the immediate and impelling necessity for relief shall be issued on or before the sixtieth day following the date of filing of the petition.

Acts 1935, No. 324, § 18; Pope's Dig., § 2081; Acts 1955, No. 31, § 1; 1975 (Extended Sess., 1976), No. 1181, § 1; 1980 (2nd Ex. Sess.), No. 4, § 1; 1981 (Ex. Sess.), No. 30, § 1; 1985, No. 523, § 1; A.S.A. 1947, § 73-217; reen. Acts 1987, No. 994, § 1.

Status: in_force

Need a lawyer in Arkansas?

Find a Arkansas lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.