Surcharge to collect rates increased by courts

Official statutory text

(a) In the event that the rates set in the order of the Arkansas Department of Transportation subsequently are determined to have been inadequate, either on rehearing or in accordance with court decision on judicial review, the public utility subject to the order shall be entitled to impose a surcharge on the affected customers for collection of the increased rates that otherwise would have been collected during the period between the effective date of the initial order and the effective date of the rates as increased, together with interest as determined by the department at a rate not to exceed the maximum interest rate otherwise allowed by law. (b) This surcharge shall be assessed over a period equal to the period between the date of the initial order and the effective date of the rates, as increased. (c) The surcharge shall be distributed among the affected customers in proportion to the amounts those customers were charged during the period between the date of the initial order and the effective date of the rates, as increased. Amended by Act 2017, No. 707,§ 126, eff. 8/1/2017. Acts 1935, No. 324, § 18; Pope's Dig., § 2081; Acts 1955, No. 31, § 1; 1975 (Extended Sess., 1976), No. 1181, § 1; 1980 (2nd Ex. Sess.), No. 4, § 1; 1981 (Ex. Sess.), No. 30, § 2; 1983, No. 911, § 1; A.S.A. 1947, § 73-217; reen. Acts 1987, No. 994, § 1.

(a) In the event that the rates set in the order of the Arkansas Department of Transportation subsequently are determined to have been inadequate, either on rehearing or in accordance with court decision on judicial review, the public utility subject to the order shall be entitled to impose a surcharge on the affected customers for collection of the increased rates that otherwise would have been collected during the period between the effective date of the initial order and the effective date of the rates as increased, together with interest as determined by the department at a rate not to exceed the maximum interest rate otherwise allowed by law.

(b) This surcharge shall be assessed over a period equal to the period between the date of the initial order and the effective date of the rates, as increased.

(c) The surcharge shall be distributed among the affected customers in proportion to the amounts those customers were charged during the period between the date of the initial order and the effective date of the rates, as increased.

Amended by Act 2017, No. 707,§ 126, eff. 8/1/2017.

Acts 1935, No. 324, § 18; Pope's Dig., § 2081; Acts 1955, No. 31, § 1; 1975 (Extended Sess., 1976), No. 1181, § 1; 1980 (2nd Ex. Sess.), No. 4, § 1; 1981 (Ex. Sess.), No. 30, § 2; 1983, No. 911, § 1; A.S.A. 1947, § 73-217; reen. Acts 1987, No. 994, § 1.

Status: in_force

Need a lawyer in Arkansas?

Find a Arkansas lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.