Revised cost and schedule estimate for developing and implementing plan; submission to commission

Official statutory text

Sec. 13. (a) If a public utility makes a substantial change in a cost and schedule estimate for developing and implementing an environmental compliance plan or a modified environmental compliance plan after the estimate has been approved by the commission under this chapter, the public utility shall file with the commission for the commission's review and approval the revised cost and schedule estimate.

(b) To the extent the commission approves a revised cost and schedule estimate, the estimate shall be the approved cost and schedule estimate for the plan.

As added by P.L.76-1991, SEC.1.

Status: in_force · Read it on the official government site

Need a lawyer in Indiana?

Find a Indiana lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.