Ind. Code § 8-1-39-12

This is the official text of Ind. Code § 8-1-39-12, part of Indiana’s Code — part of the compiled statutory law of Indiana, published by the state as "Code." Browse the sections below, each linked to its official government source.

Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.

Commission hearing and order on TDSIC petition; examination by utility consumer counselor and intervenors; new projects or improvements

Official statutory text

Sec. 12. (a) Not more than one hundred twenty (120) days after a public utility files a petition under section 9 of this chapter, the commission shall conduct a hearing and issue an order on the petition.

(b) Not more than sixty (60) days after a public utility files a petition under section 9 of this chapter, the office of the utility consumer counselor and other intervenors, if any, may:

(1) examine the information of the public utility to confirm that the proposed transmission, distribution, and storage system improvements comply with this chapter; and

(2) report its findings to the commission.

(c) If the commission determines that the petition satisfies the requirements of this chapter and the capital expenditures and TDSIC costs are reasonable, the commission shall approve the petition, including:

(1) capital expenditures;

(2) timely recovery of TDSIC costs, including costs associated with a targeted economic development project, through a TDSIC; and

(3) if requested, authority to defer TDSIC costs under section 9(c) of this chapter.

(d) If the public utility has requested approval of new targeted economic development projects or new transmission, distribution, and storage system improvements under section 9(b) of this chapter, the commission's order must include the following:

(1) A finding of the best estimate of the cost of the new projects or improvements.

(2) A determination whether public convenience and necessity require or will require the new projects or improvements.

(3) A determination whether the estimated costs of the new projects or improvements are justified by incremental benefits attributable to the new projects or improvements.

If the commission determines that the public utility's new projects or improvements are reasonable, the commission shall approve the new projects or improvements and authorize TDSIC treatment for the new projects or improvements.

As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019, SEC.6.

Status: in_force · Read it on the official government site

Need a lawyer in Indiana?

Find a Indiana lawyer
About this page: Statute text is reproduced from official government publishers via the Open US Law dataset (Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine (Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.