Ind. Code § 8-1-42-19
This is the official text of Ind. Code § 8-1-42-19, part of Indiana’s Code — part of the compiled statutory law of Indiana, published by the state as "Code." Browse the sections below, each linked to its official government source.
Not legal advice. This page reproduces the official text of a government statute for reference only. Laws change, and how a statute applies depends on your specific facts. For advice about your situation, consult a licensed attorney in your state.
CSE system's failure to generate electricity; presumed abandonment; required removal of project assets; project owner's failure to remove assets; removal of assets by permit authority; recovery of costs
Official statutory text
Sec. 19. (a) If a CSE system installed in a unit does not generate electricity for eighteen (18) consecutive months:
(1) the CSE system is considered abandoned as of the date that is five hundred forty (540) days after the date on which the CSE system last generated electricity; and
(2) all CSE system project assets shall be removed in accordance with section 18(c) of this chapter not later than one (1) year after the date of abandonment specified in subdivision (1).
(b) In the case of abandonment, as described in subsection (a), if the project owner fails to remove the CSE system project assets not later than one (1) year after the date of abandonment, as required by subsection (a)(2), the permit authority may engage qualified contractors to:
(1) enter the project site;
(2) remove the CSE system project assets;
(3) sell any assets removed; and
(4) remediate the site;
and may initiate proceedings to recover any costs incurred.
As added by P.L.90-2022, SEC.2.
(1) the CSE system is considered abandoned as of the date that is five hundred forty (540) days after the date on which the CSE system last generated electricity; and
(2) all CSE system project assets shall be removed in accordance with section 18(c) of this chapter not later than one (1) year after the date of abandonment specified in subdivision (1).
(b) In the case of abandonment, as described in subsection (a), if the project owner fails to remove the CSE system project assets not later than one (1) year after the date of abandonment, as required by subsection (a)(2), the permit authority may engage qualified contractors to:
(1) enter the project site;
(2) remove the CSE system project assets;
(3) sell any assets removed; and
(4) remediate the site;
and may initiate proceedings to recover any costs incurred.
As added by P.L.90-2022, SEC.2.
Status: in_force · Read it on the official government site
Need a lawyer in Indiana?
Find a Indiana lawyer
About this page: Statute text is reproduced from official government publishers via the