§ 53.056.
Official statutory text
Sec. 53.056. DERIVATIVE CLAIMANT: NOTICE TO OWNER AND ORIGINAL CONTRACTOR. (a) Except as provided by Section 53.057, a claimant other than an original contractor must give the notice prescribed by Subsections (a-1) and (a-2) for the lien to be valid.
(a-1) For all unpaid labor or materials provided, the claimant must send a notice of claim for unpaid labor or materials to the owner or reputed owner and the original contractor. The notice must be sent:
(1) for projects other than residential construction projects, not later than the 15th day of the third month after the month during which:
(A) the labor or materials were provided; or
(B) the undelivered specially fabricated materials would normally have been delivered; or
(2) for residential construction projects, not later than the 15th day of the second month after the month during which:
(A) the labor or materials were provided; or
(B) the undelivered specially fabricated materials would normally have been delivered.
(a-2) The notice must be in substantially the following form:
"Date:_______________
"Project description and/or address: _______________
"Claimant's name: _______________
"Type of labor or materials provided: _______________
"Original contractor's name: _______________
"Party with whom claimant contracted if different from original contractor: _______________
"Claim amount: _______________
"_______________ (Claimant's contact person)
"_______________ (Claimant's address)"
(a-3) The notice may include an invoice or billing statement.
(a-4) A claimant may give to the original contractor a written notice of an unpaid labor or materials invoice that is past due. A notice under this subsection is not required for a lien to be valid.
(b) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(c) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(d) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(e) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(f) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(a-1) For all unpaid labor or materials provided, the claimant must send a notice of claim for unpaid labor or materials to the owner or reputed owner and the original contractor. The notice must be sent:
(1) for projects other than residential construction projects, not later than the 15th day of the third month after the month during which:
(A) the labor or materials were provided; or
(B) the undelivered specially fabricated materials would normally have been delivered; or
(2) for residential construction projects, not later than the 15th day of the second month after the month during which:
(A) the labor or materials were provided; or
(B) the undelivered specially fabricated materials would normally have been delivered.
(a-2) The notice must be in substantially the following form:
"Date:_______________
"Project description and/or address: _______________
"Claimant's name: _______________
"Type of labor or materials provided: _______________
"Original contractor's name: _______________
"Party with whom claimant contracted if different from original contractor: _______________
"Claim amount: _______________
"_______________ (Claimant's contact person)
"_______________ (Claimant's address)"
(a-3) The notice may include an invoice or billing statement.
(a-4) A claimant may give to the original contractor a written notice of an unpaid labor or materials invoice that is past due. A notice under this subsection is not required for a lien to be valid.
(b) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(c) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(d) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(e) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
(f) Repealed by Acts 2021, 87th Leg., R.S., Ch. 690 (H.B. 2237), Sec. 36(4), eff. January 1, 2022.
Status: repealed · Read it on the official government site
Dealing with a real estate matter in Texas?
See all Texas Real Estate lawyers
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.