(a) The board shall establish standards for determining the amount of the supplemental grant funding to be made available for each project under this article.
(1) For a project application qualifying for funding under paragraph (1) of subdivision (b) of Section 17077.40, the supplemental grant shall be in the form of an adjustment to the per-pupil eligibility of the project. This per-pupil eligibility adjustment shall be calculated to cover costs associated with the project that are uniquely related to the joint-use nature of the project, including, but not limited to, any increased costs associated with planning the joint-use aspect of the project.
(2) For a project application qualifying under paragraph (2) or (3) of subdivision (b) of Section 17077.40, the supplemental grant may be provided without regard to the existence of per-pupil eligibility pursuant to this chapter, and may be expressed on a per-square-foot cost basis, on a per-pupil cost basis, or on a per-project cost basis.
(b) Notwithstanding any other provision of this chapter, project costs may exceed the board’s standards established pursuant to subdivision (a) only if the excess is paid completely by local or joint-use partner sources.
(c) On July 1 of each year the board shall apportion to qualifying applicant school districts those funds that it determines are available for the purpose of this article. The board shall not release funds to a qualifying applicant until the project plans have received all approval required pursuant to this chapter, including, but not limited to, the approval of the Division of the State Architect. If the project does not receive all necessary plan approvals within one year of the date of the apportionment, the board shall rescind the apportionment.
(d) If the total funding for the purposes of this article is not sufficient to fund all of the joint-use projects for funding under this article, the board shall first fund projects eligible under paragraphs (1), (2), and (3) of subdivision (b) of Section 17077.40 in that order. The board may establish other priority standards within that order, as necessary.
(e) Except as expressly provided in this article, projects funded pursuant to this article shall comply with all other requirements of this chapter, except for Article 11 (commencing with Section 17078.10), which shall apply only to projects under this article if they also qualify for funding under Article 11 (commencing with Section 17078.10).
(1) For a project application qualifying for funding under paragraph (1) of subdivision (b) of Section 17077.40, the supplemental grant shall be in the form of an adjustment to the per-pupil eligibility of the project. This per-pupil eligibility adjustment shall be calculated to cover costs associated with the project that are uniquely related to the joint-use nature of the project, including, but not limited to, any increased costs associated with planning the joint-use aspect of the project.
(2) For a project application qualifying under paragraph (2) or (3) of subdivision (b) of Section 17077.40, the supplemental grant may be provided without regard to the existence of per-pupil eligibility pursuant to this chapter, and may be expressed on a per-square-foot cost basis, on a per-pupil cost basis, or on a per-project cost basis.
(b) Notwithstanding any other provision of this chapter, project costs may exceed the board’s standards established pursuant to subdivision (a) only if the excess is paid completely by local or joint-use partner sources.
(c) On July 1 of each year the board shall apportion to qualifying applicant school districts those funds that it determines are available for the purpose of this article. The board shall not release funds to a qualifying applicant until the project plans have received all approval required pursuant to this chapter, including, but not limited to, the approval of the Division of the State Architect. If the project does not receive all necessary plan approvals within one year of the date of the apportionment, the board shall rescind the apportionment.
(d) If the total funding for the purposes of this article is not sufficient to fund all of the joint-use projects for funding under this article, the board shall first fund projects eligible under paragraphs (1), (2), and (3) of subdivision (b) of Section 17077.40 in that order. The board may establish other priority standards within that order, as necessary.
(e) Except as expressly provided in this article, projects funded pursuant to this article shall comply with all other requirements of this chapter, except for Article 11 (commencing with Section 17078.10), which shall apply only to projects under this article if they also qualify for funding under Article 11 (commencing with Section 17078.10).
Status: in_force · Read it on the official government site
Need a lawyer in California?
Find a California lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.