Limit on increase in utility's total retail revenues resulting from TDSIC; combined revenue impact of TDSIC under terminated plan and TDSIC under new plan
Official statutory text
Sec. 14. (a) The commission may not approve a TDSIC that would result in an average aggregate increase in a public utility's total retail revenues of more than two percent (2%) in a twelve (12) month period. For purposes of this subsection, a public utility's total retail revenues do not include TDSIC revenues associated with a targeted economic development project.
(b) If a public utility incurs TDSIC costs under the public utility's TDSIC plan that exceed the percentage increase in a TDSIC approved by the commission, the public utility shall defer recovery of the TDSIC costs as set forth in section 9(c) of this chapter.
(c) For purposes of subsection (a), in the case of a public utility that terminates a TDSIC plan under section 10(d) of this chapter, the commission shall consider the combined twelve (12) month revenue impact of the TDSIC approved under the terminated plan and the TDSIC approved under any new TDSIC plan.
As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019, SEC.7.
(b) If a public utility incurs TDSIC costs under the public utility's TDSIC plan that exceed the percentage increase in a TDSIC approved by the commission, the public utility shall defer recovery of the TDSIC costs as set forth in section 9(c) of this chapter.
(c) For purposes of subsection (a), in the case of a public utility that terminates a TDSIC plan under section 10(d) of this chapter, the commission shall consider the combined twelve (12) month revenue impact of the TDSIC approved under the terminated plan and the TDSIC approved under any new TDSIC plan.
As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019, SEC.7.
Status: in_force · Read it on the official government site
Need a lawyer in Indiana?
Find a Indiana lawyer
About this page: Statute text is reproduced from official government publishers via the
Open US Law dataset
(Vaquill AI, snapshot v2026.08, CC BY 4.0). Primary legislative text like this is public domain under the government-edicts doctrine
(Georgia v. Public.Resource.Org, 2020). We link every section back to its official source so you can verify it independently.